We run our projects during the University of York's academic term dates (terms 1, 2 and 3). Each of our projects last one academic term throughout which we will have regular team, external mentor and client meetings. Below is a guide timeline.

  • Week 1 Receive terms of reference
  • Week 2-3 Appoint Strategy Partners, Development Officers, External Mentor, Project Manager and team of consultants
  • Week 4 Initial consultation with client
  • Week 5 Produce Statement of Work and pitch it to the committee
  • Week 6 Send the finalised Statement of Work to the client
  • Weeks 6-9 Conduct research and complete Final Presentation
  • Week 9 Final Presentation is scrutinised by the Committee and the External Mentor
  • Week 10 Presentation to the client with the opportunity for clients to ask questions and delve further in to consultants’ findings